# A bundle plan sequences each product with its own owner, so one late module does not stall the others

Template, Multi-product bundle, read 10 Nov 2026

**The short answer.** Thirteen steps over about ninety days. The template gives each product its own set of steps, a shared contract and a single go-live sequence, so the buyer sees which module goes live in which order, who owns each one, and what the bundle as a whole must achieve.

## When to use it

Use when the buyer is purchasing two or more products or modules in one contract, each with its own implementation team or stakeholder.

## The plan, step by step

Day 0 to day 90

| Day | Step | Owner | Side | Done when |
| --- | --- | --- | --- | --- |
| 0 | Agree the bundle goal | Buyer: executive sponsor | buyer | One goal is on the plan with a measure for the whole bundle. |
| 3 | List the products and their buyer owners | Both: account executive and sponsor | both | Each product has a named buyer owner. |
| 6 | Set the go-live order | Both: account executive and sponsor | both | The order and the reason for it are on the plan. |
| 10 | Confirm technical dependencies between products | Seller: solutions architect | seller | Dependencies are listed and ordered. |
| 14 | Run a demo per product | Seller: solutions engineer | seller | Each product owner has attended their demo. |
| 24 | Agree the pricing structure | Both: account executive and procurement | both | One price sheet shows each product and the bundle total. |
| 30 | Complete security review for all products | Buyer: IT or security lead | buyer | One review covers all products, or exceptions are listed. |
| 45 | Negotiate one contract | Both: legal contacts | both | The final text covers all products. |
| 55 | Obtain signature | Buyer: economic buyer | buyer | The signed contract is on record. |
| 58 | Create a plan per product | Seller: customer success manager | seller | Each product has an onboarding plan with a buyer owner. |
| 60 | Start the first product | Both: product owners | both | The first product is live in test or production as agreed. |
| 75 | Start the dependent products | Both: product owners | both | Each dependent product starts on its date. |
| 90 | Review the bundle goal | Seller: customer success manager | seller | The goal measure is reviewed against actual results. |

## Where plans like this stall

- Selling the bundle to one sponsor and meeting the product owners only after signature.
- Hiding dependencies, which makes the later products late.
- Using a single onboarding owner for every module.

## Running it in a tool

The [MAP Tool Matrix](/tools/) shows which tools keep the plan where the buyer already is, send nudges and sync to the CRM; [the tool ranking](/platforms/) weighs the plan at 30 of 100.

## Sources

- Dock: mutual action plan page, templates and multi-phase plans: https://www.dock.us/features/mutual-action-plan (read 10 Nov 2026)
- GUIDEcx: Salesforce integration and project templates: https://www.guidecx.com/products/integrations/salesforce/ (read 10 Nov 2026)
- HubSpot knowledge base: deal plan templates with owners and day offsets: https://knowledge.hubspot.com/records/keep-buyers-on-track-with-deal-plans (read 10 Nov 2026)

Last reviewed 10 Nov 2026. Canonical: https://themutualactionplan.com/templates/multi-product-bundle/