# A public sector plan follows the buyer's procurement rules and puts every formal date on the calendar

Template, Public sector, read 10 Nov 2026

**The short answer.** Fourteen steps. The template assumes a formal process with published requirements, a response deadline and an award notice. It puts each formal date on the plan with a buyer owner, and the seller's tasks are the documents the buyer must receive by those dates.

## When to use it

Use when the buyer is a government body, agency or publicly funded institution and the purchase follows a procurement process, tender or framework.

## The plan, step by step

Day 0 to day 85

| Day | Step | Owner | Side | Done when |
| --- | --- | --- | --- | --- |
| 0 | Identify the buying route | Seller: bid manager | seller | The route (tender, framework, direct award or quote) is confirmed with the buyer contact. |
| 3 | Obtain the requirements and timetable | Buyer: procurement officer | buyer | The documents and all formal dates are on the plan. |
| 5 | Decide to bid | Seller: sales director | seller | A bid decision is recorded with the reason. |
| 8 | Submit clarification questions | Seller: bid manager | seller | Questions are sent by the buyer's deadline and the receipt is saved. |
| 12 | Receive the buyer's answers | Buyer: procurement officer | buyer | Answers are logged on the plan. |
| 20 | Draft the response | Seller: solutions architect | seller | A complete draft is reviewed internally against every requirement. |
| 25 | Complete security and data protection forms | Seller: security contact | seller | All forms are complete and checked by a second person. |
| 28 | Obtain legal and pricing approval | Seller: deal desk lead | seller | Written internal approvals are attached. |
| 30 | Submit the response | Seller: bid manager | seller | The submission receipt is saved before the deadline. |
| 45 | Attend the evaluation or presentation | Both: account executive and evaluation panel | both | The presentation date is held and any follow-up questions are logged. |
| 60 | Receive the award notice | Buyer: procurement officer | buyer | The notice is on the plan, with any standstill period dates. |
| 70 | Agree contract text | Both: legal contacts | both | The final text is agreed under the buyer's terms. |
| 80 | Obtain signatures and purchase order | Buyer: authorized signatory | buyer | The signed contract and order number are on record. |
| 85 | Plan the start of service | Both: customer success manager and buyer lead | both | The kickoff date and onboarding steps are added. |

## Where plans like this stall

- Missing a formal deadline, which can end the bid regardless of merit.
- Contacting evaluators outside the permitted channel.
- Assuming the buyer's staff can open outside links; confirm the format of the plan before sharing it.

## Running it in a tool

The [MAP Tool Matrix](/tools/) shows which tools keep the plan where the buyer already is, send nudges and sync to the CRM; [the tool ranking](/platforms/) weighs the plan at 30 of 100.

## Sources

- MEDDICC, MEDDPICC methodology: decision process and paper process: https://meddicc.com/meddpicc-sales-methodology-and-process (read 10 Nov 2026)